Schedule of Condition
The dated record of a neighbouring property taken before work starts — and the document that decides damage disputes
A Schedule of Condition is a dated, indexed record of the condition of a neighbouring property made before building work begins. It combines written notes room by room with numbered photographs, and where existing cracking or movement matters, measurements taken on site. It is produced under the Party Wall etc. Act 1996 process and it exists for one reason: to answer the question every damage claim turns on — was that crack caused by the work, or was it there already?
A Schedule of Condition is the evidence that decides whether damage found after the work was caused by the work. Without one, that question is genuinely unwinnable for either side, because it becomes one owner's recollection against the other's. Grey & Associates carry out Schedules of Condition across London for £620 plus VAT per property.
It is the least understood document in the whole process, and the one that decides the most. Clients usually come to it expecting a formality; they leave understanding that it is the only part of the file that will still matter in six months' time, when a hairline crack has become a claim.
What a Schedule of Condition records
A proper schedule is exhaustive about the things that change and the things that are already imperfect. The second category is what makes it useful — a record that says everything was in good order is not credible in a Victorian terrace, and it will not help anyone when a crack appears next to a pre-existing one.
Inside the neighbouring property
- Cracks and their position, direction, width and length, numbered and indexed
- Plaster, ceilings, cornices, coving and any historic repair
- Decoration, tiling and finishes, and the standard they are in
- Floors, thresholds, door and window operation and alignment
- Cellars and lower ground floors, where damp often already exists
- Any existing damp and its extent, recorded as found rather than diagnosed
Outside, and the structure
- External brickwork, render, pointing and any existing movement
- Garden walls, boundary walls and outbuildings
- Drainage runs, gullies and any visible defect
- Roof coverings, flashings and parapets visible from the neighbouring property
- Ground levels and any existing paving or hardstanding near the works
- Numbered photographs, dated, and indexed to the notes
On basements and underpinning the schedule carries more weight again, which is why the basement specialism page treats it as the central document in the case. Water, tanking, sumps and the existing cellar condition all need recording before a dig begins, because ingress and movement are the two claims that follow a neighbouring basement most often.
How the schedule is carried out
- Access by appointment. The neighbouring property is inspected with the owner, or their surveyor, present wherever possible. Being there matters: it removes any later argument about whether something was recorded as found.
- A room-by-room inspection, working through the property in order and noting condition against a numbered index so that every photograph and every observation can be located precisely.
- Photographs, dated and indexed. Wide shots to establish the room, close shots for each defect, and a scale where a crack width is being recorded. The photographs are the part of the schedule that gets looked at when a claim arises.
- Monitoring where movement is the risk. Tell-tales or gauges fitted across existing cracks during the same visit, read on a later appointment. For excavation work this converts an opinion about movement into a measurement of it.
- A copy to both owners. The schedule is agreed and shared, not held by one side, because an unshared record is worth very little when it is produced three months later.
One point of honesty about what this is. A Schedule of Condition records rather than advises. It is not a structural survey, it is not a valuation, and it does not tell the neighbour whether their property has a problem worth fixing. If a surveyor sees something serious while making the schedule, they will say so — but the purpose of the document is to fix a baseline, and the scope follows from that.
When you need one
The Act does not name a Schedule of Condition, and no section of it requires one. What happens instead is that the adjoining owner's surveyor asks for it, or makes it a condition of the award — which in practice amounts to the same thing on any case that is worth protecting.
- Where the adjoining owner dissents, or does not respond. The schedule is the first piece of work a surveyor does on the neighbouring property, because the award depends on it.
- Where work is excavation under section 6. Basement digs, new foundations and drainage near a neighbouring structure. The risk is movement and water, and the schedule is the measurement baseline.
- Where the building is old, or already cracked. Victorian and Edwardian terraces, aged plaster, historic settlement. A record of what is already there is worth more in exactly the properties where damage claims are most likely.
- Where works are extensive or long-running. Underpinning, temporary works, loft and rear extensions that open up a shared wall over months rather than weeks.
- Where the adjoining owner asks for one. It is a reasonable request and it is normally granted. A building owner who refuses is storing up a problem rather than avoiding a cost.
Where it is a modest, quickly finished job and the neighbours are on good terms, a consent with a written licence covering a schedule is a lighter route than a full dispute. Our page on party wall notices sets out how consent, dissent and silence each change what happens next.
What happens at completion
The schedule does its second job at the end of the works, when the surveyor returns and compares the property with the record taken before anyone started.
- Nothing has changed. The case closes and the building owner is discharged from the claims that would otherwise follow. This is the most common outcome, and it is the outcome the schedule makes demonstrable rather than merely asserted.
- Damage is identified. The making-good obligation in the award applies, and the contractor returns to put it right to the standard the award requires.
- Loss cannot sensibly be made good. Section 7(2) puts the building owner under a duty to compensate the adjoining owner for loss or damage caused by work executed under the Act, whether or not anyone was at fault. That is a statutory duty, not a question of negligence, and it applies to the decoration, the tiling and the inconvenience as well as to the structure.
- There is a dispute about cause. This is where the pre-works record earns its cost: existing cracks are already documented, positions and widths are recorded, and the argument moves from recollection to evidence.
For the adjoining owner, that sequence is the whole value of responding to a notice. For the building owner, it is what stands between a completed project and an open-ended claim. Both sides benefit from the same document, which is why it survives every change in the way these cases are run.
What a Schedule of Condition costs
Our fee is £620 plus VAT per property. A separate schedule and fee applies to each adjoining property affected, so a house with two neighbours needs two notices and two schedules. Where a dispute has arisen, the building owner carrying out the work is responsible for the reasonable fees of both sides' surveyors under section 11 of the Act, which means the adjoining owner is not paying for their own protection in the normal case.
Basement and underpinning schemes sit outside the standard fee because the scheduling, monitoring and engineering input is far greater. The basement package is published separately: £250 to serve notice, £1,100 per Schedule of Condition and £1,050 for the award, £2,400 plus VAT in total per adjoining property. Full detail is on our party wall surveyor fees page.
Set against what it protects, the arithmetic is straightforward. A schedule costs less than a day of a contractor's time on site, and it is the difference between a damage claim that can be resolved with a photograph and one that ends up in front of a judge.
Schedule of Condition — frequently asked questions
What is a Schedule of Condition?
A Schedule of Condition is a dated, indexed record of the condition of a neighbouring property made before building work starts. It combines written notes room by room with numbered photographs, and where relevant measurements of existing cracks and movement. It is not a valuation and it is not a structural survey for the neighbour's benefit — it records what is there, so that any later damage can be attributed rather than argued about.
Is a Schedule of Condition required by the Party Wall Act?
The Act does not name a Schedule of Condition, and there is no section that requires one. It is nonetheless standard practice, and in most London cases the adjoining owner's surveyor will require one, or make it a condition of the award. Where work involves excavation under section 6 — basement digs and underpinning in particular — a Schedule of Condition is close to essential, because it is the pre-works record against which any movement is measured.
How much does a Schedule of Condition cost?
Grey & Associates charge £620 plus VAT per property for a Schedule of Condition, and a separate schedule and fee applies to each adjoining property affected. Basement and underpinning schemes are priced differently, because the scheduling and engineering input is far greater: our basement package is £1,100 plus VAT per Schedule of Condition, within a £2,400 plus VAT total per adjoining property covering notice, schedule and award.
Who pays for a Schedule of Condition?
Where a dispute arises, the building owner carrying out the work is responsible for the reasonable fees of both sides' surveyors under section 11 of the Party Wall etc. Act 1996. In practice that means the Schedule of Condition on the neighbouring property is the building owner's cost, and the adjoining owner is not paying for their own protection in the normal case.
Can my neighbour refuse access for a Schedule of Condition?
In practice access is arranged by appointment and almost always agreed, because the Schedule of Condition exists to protect the neighbour. The Act does provide powers of entry for the purposes of the Act, with notice required except in an emergency, and where a neighbour refuses access the matter can be dealt with as part of the dispute and written into the award. Refusing access does not stop the works; it removes the protection the neighbour would otherwise have.
How long does a Schedule of Condition take?
The inspection itself takes one to three hours on site for a typical London terrace house, depending on the size of the property and how much of it needs recording. The written and photographic report follows within a few days. Where existing cracking needs monitoring, small gauges may be fitted during the same visit and read on a later one, which adds a second appointment.
Does a Schedule of Condition protect me if my neighbour damages my wall?
It is the single most useful document you can have. Section 7(2) of the Party Wall etc. Act 1996 puts the building owner under a duty to compensate the adjoining owner for loss or damage caused by work carried out under the Act, whether or not anyone was negligent. Proving that damage was caused by the work is the difficulty, and the Schedule of Condition is what resolves it: without a pre-works record, causation becomes one party's word against the other's.
What happens to the Schedule of Condition at the end of the works?
It is the baseline for the completion inspection. The surveyor returns, compares the property with the record, and reports whether anything has changed. Where damage is identified, the making-good obligation in the award applies, and where the loss cannot be made good physically, section 7(2) compensation applies instead. Where nothing has changed, the schedule is also what discharges the building owner from the claims that would otherwise follow.
Arrange a Schedule of Condition
Whether you are building and want the neighbouring property recorded before you start, or you have received a notice and want your property protected, the first conversation is free.
- Schedules of Condition carried out across London — £620 plus VAT per property.
- Indexed photographs and, where movement is a risk, monitoring gauges.
- A completion inspection compared against the pre-works record.
- Cover across South and West London, and Greater London within the M25.
Call 020 8150 3762 or email info@greyandassociates.co.uk.
Related: party wall surveyors in London, party wall notices, party wall awards, our published fees, and basement and underpinning schemes. For why the schedule matters when a neighbour does nothing, see what happens if your neighbour ignores your notice.